Mexico Energy Partners

Onsite solar built around the facility, not the roof

Independent technical and commercial advice for solar, storage and onsite PPA decisions in Mexico. MEP sells no panels and takes nothing from developers.

3 modelsCAPEX, lease and onsite PPA compared on one basis
0.7 MWnew distributed generation limit under the 2025 electricity law
0developer commissions
Request a feasibility review

No developer contact. Confidential.

Regulatory figures as of 19 September 2026.

Confidential solar feasibility review

Share one recent electricity bill and a roof drawing or site plan. MEP identifies the information needed for a defensible technical and commercial screen.

Enter your name.
Enter a valid work email.
Enter your company.
Enter a valid phone number.
Select your current supply.
Please accept the privacy notice.

Next step: after you submit, reply to our email with one recent electricity bill and a roof or site plan.

Prefer email? Send the bill and site plan to info@mexicoenergypartners.com

Project value begins with load match and operating horizon

Load match

The value of generation depends on when the facility consumes power, not only on annual production.

Site fit

Roof, land, structural condition, electrical interfaces and interconnection define what can be built safely.

Operating horizon

Term, facility plans, maintenance and capital priorities determine which commercial structure is defensible.

Price becomes meaningful only after these three conditions are established.

Solar alone does not lower the punta demand charge

Under GDMTH, CFE bills capacity on your maximum demand during the punta period, a late-day window in most regions. Solar output has fallen away by then. A system sized on annual kWh can cut the energy charge and leave the capacity charge where it was.

MEP models the interval profile first, then tests whether storage or load shifting pays for itself. CNE storage rules published in April 2026 allow batteries that share the facility's connection point to operate without a separate permit, and explicitly allow peak shaving.

Choose the commercial model after the facility screen

Installer and developer pages each sell one financing product. MEP compares lifetime cost, retained risk, accounting implications and operating flexibility across all three before procurement.

CAPEXLeaseOnsite PPA
CommitmentOwn the systemPreserve capital flexibilityBuy energy under contract
Upfront capitalFull project costLowNone
Who owns the systemYouLessor during the term, per contractDeveloper
Performance riskYou, backed by contractor warrantiesShared, per contractDeveloper, per production guarantees
Tax treatment100% first-year deduction available under LISR Art. 34-XIII if the system operates for at least five yearsLease payments, per contract structureEnergy payments as an operating expense
Best whenCapital is available, the operating horizon is long and the facility wants full ownershipPayment timing and equipment ownership need to match budget and balance-sheet prioritiesA developer funds the project and the buyer accepts a long-term operating agreement
Get a side-by-side for your siteNo developer contact. Confidential.

Tax points are general. Confirm treatment with your tax adviser.

An onsite PPA is a long-term operating contract

Price and escalation

Energy price, indexation, taxes, pass-throughs and the savings definition.

Performance

Availability, production guarantees, degradation, metering and remedies.

Operating control

Maintenance access, outages, curtailment, safety and facility coordination.

End of term

Buyout, removal, extension, roof restoration and change in facility use.

The contract remains relevant long after construction is complete.

The rules in plain terms

Distributed generation in Mexico passed 5 GW at the end of 2025, almost all solar. The 2025 electricity law changed the thresholds that decide which route a project takes.

Under 0.7 MW

Distributed generation. No generation permit. Connects to the CFE distribution grid under an interconnection contract, with net metering and net billing still in use. The 2025 law raised the limit from 0.5 MW. Secondary DG rules are still being updated.

0.7 MW and above

Interconnected self-consumption. Requires a CNE generation permit, with a simplified route for 0.7 to 20 MW, and an interconnection agreement.

Surplus energy

Above the DG limit, surplus can be delivered to the grid without payment or sold only to CFE, which is not obliged to buy it.

Backup and storage

Intermittent self-consumption plants must add storage or pay CFE for backup. Co-located batteries need no separate permit.

As of 19 September 2026. Verify current rules before relying on this page.

Technical diligence makes bids comparable

Each installer quotes its own energy model on its own assumptions. MEP sets one technical basis so every bid is priced against the same facts.

Bid comparison matrix and savings roadmap documents

Structural basis

Roof zones, loading, remaining roof life, drainage, wind and access.

Electrical basis

Connection point, protection, transformer capacity, metering and controls.

Energy model

Weather source, losses, degradation, availability, clipping and load match.

Interconnection

Application route, studies, responsibilities, timing and operating limits.

Resolve material risks before signing

Roof and structure

Remaining roof life, loading, drainage, access and restoration obligations.

Interconnection

Schedule, studies, upgrades, operating limits and allocation of responsibility.

Energy model

Assumptions, losses, curtailment, degradation and production guarantees.

Developer credit

Construction capacity, warranties, security, step-in rights and continuity.

Facility change

Expansion, shutdown, relocation, load change and early termination.

Operations

Maintenance access, safety, outages, metering, reporting and the dispute process.

Request a feasibility reviewNo developer contact. Confidential.

One mandate carries the project into operation

Assess

Load, site, structure and interconnection.

Structure

CAPEX, lease and onsite PPA comparison.

Procure

Comparable technical and commercial bids.

Oversee

Contract, construction and commissioning.

Verify

Production, invoices, savings and performance.

MEP works for the facility, not the developer

0panel or equipment sales
0developer commissions
Clientpays all MEP advisory fees

Recommendations are evaluated against facility requirements. MEP has no economic interest in which developer, installer, panel brand or financing model is selected.

Independence is a governance control.

What facility and finance teams ask first

Do we need a generation permit?

Not below 0.7 MW, which is distributed generation under the 2025 law. At 0.7 MW and above, interconnected self-consumption needs a CNE permit, with a simplified route up to 20 MW.

Can we sell surplus energy?

Distributed generation still uses net metering and net billing. At 0.7 MW and above, surplus can go to the grid without payment or be sold only to CFE, which is not obliged to buy it. MEP sizes the system so surplus does not carry the business case.

How long are onsite PPA terms?

Offers in the Mexican market run from 5 to 25 years. The term should match your operating horizon for the site, with buyout, extension and removal terms written in before signing.

What if we expand, relocate or shut down the site?

That is a contract question, not a technical one. MEP negotiates facility-change, assignment and early-termination terms before signing, so the PPA does not outlast the plant's plans.

Is our roof suitable?

It depends on remaining roof life, structural loading, drainage and access. A roof that needs replacement in eight years changes the economics of a 20-year system. A roof drawing lets MEP flag this early.

Why not go straight to installers?

You will, through a competitive process MEP runs. Installers quote their own product and financing on their own assumptions. MEP puts every bid on the same energy model, technical basis and contract terms so they can be compared.

Begin with a confidential solar feasibility review

Share one recent electricity bill and available roof drawings or a site plan. MEP will identify the information needed for a defensible technical and commercial screen, before any developer sees your data.

No developer contact. Confidential.

Finance lead reviewing a CFE bill next to an interval load profile

Request a feasibility review

Share one recent electricity bill and a roof drawing or site plan. MEP identifies the information needed for a defensible technical and commercial screen.

Enter your name.
Enter a valid work email.
Enter your company.
Enter a valid phone number.
Select your current supply.
Please accept the privacy notice.

Next step: after you submit, reply to our email with one recent electricity bill and a roof or site plan.

Prefer email? Send the bill and site plan to info@mexicoenergypartners.com

Request a feasibility review